CABIN 300 — PRELIMINARY INSTALLATION OVERVIEW Status: Planning overview only. Not an installation manual. 1. Confirm site access, survey and jurisdiction requirements. 2. Complete project-specific foundations and underground utilities. 3. Coordinate transport, crane access, staging and inspection sequence. 4. Receive the factory-completed cabin and inspect prior to lift. 5. Place the cabin using an approved lift plan and qualified crew. 6. Complete structural, weather and building-service connections. 7. Commission systems, complete inspections and document handover. Typical field installation target: four people over three to five days after site readiness. Actual duration varies by site, access, weather, inspection and utility conditions.